WHSIT0607ImprovementPLan





Project Start:
Project Finish:
Sun 10/8/06
Thu 6/21/07


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
IT Improvement Plan
191 days?Thu 9/28/06Thu 6/21/07 14%
2
Define project accountability
176 daysThu 10/19/06Thu 6/21/07 0%
3
Report Progress to the Board
176 daysThu 10/19/06Thu 6/21/07 0%
4
Report Progress to the Board 1
1 dayThu 10/19/06Thu 10/19/06 0%
5
Report Progress to the Board 2
1 dayThu 11/16/06Thu 11/16/06 0%
6
Report Progress to the Board 3
1 dayThu 12/21/06Thu 12/21/06 0%
7
Report Progress to the Board 4
1 dayThu 1/18/07Thu 1/18/07 0%
8
Report Progress to the Board 5
1 dayThu 2/15/07Thu 2/15/07 0%
9
Report Progress to the Board 6
1 dayThu 3/15/07Thu 3/15/07 0%
10
Report Progress to the Board 7
1 dayThu 4/19/07Thu 4/19/07 0%
11
Report Progress to the Board 8
1 dayThu 5/17/07Thu 5/17/07 0%
12
Report Progress to the Board 9
1 dayThu 6/21/07Thu 6/21/07 0%
13
Define project resources
6 days?Thu 9/28/06Thu 10/5/06 100%
14
Define Human Resources
6 days?Thu 9/28/06Thu 10/5/06 100%
15
Enlist Communications Committee
6 days?Thu 9/28/06Thu 10/5/06EAK100%
16      
17
Infrastructure Reliability
1 day?Mon 10/9/06Mon 10/9/06 0%
18
Inventory current IT environment
1 day?Mon 10/9/06Mon 10/9/06 0%
19
Applications
1 day?Mon 10/9/06Mon 10/9/06 0%
20
Hardware
1 day?Mon 10/9/06Mon 10/9/06 0%
21
Software
1 day?Mon 10/9/06Mon 10/9/06 0%
22
Establish Service Level Standards
1 day?Mon 10/9/06Mon 10/9/06 0%
23
Establish back-up and recovery plan
1 day?Mon 10/9/06Mon 10/9/06 0%
24
Establish Training and support plan
1 day?Mon 10/9/06Mon 10/9/06 0%
25
Assess required expertise and resources to support infrastructure
1 day?Mon 10/9/06Mon 10/9/06 0%
26
Assess in-house, on-call, and external hosting alternatives
1 day?Mon 10/9/06Mon 10/9/06 0%
27
Establish relationships and practices
1 day?Mon 10/9/06Mon 10/9/06 0%
28
Implement Infrastucture Syupport Plan Plan
1 day?Mon 10/9/06Mon 10/9/06 0%
29      
30
Applications Enhancement
40 days?Mon 10/9/06Fri 12/1/06 0%
31
SIPS
40 days?Mon 10/9/06Fri 12/1/06 0%
32
Assess functional requirements.specifiacations
1 day?Mon 10/9/06Mon 10/9/06 0%
33
Develop functional checklist
1 day?Mon 10/9/06Mon 10/9/06 0%
34
Assess Alternatives
1 day?Mon 10/9/06Mon 10/9/06 0%
35
Centerpoint
1 day?Mon 10/9/06Mon 10/9/06 0%
36
Powerschool
1 day?Mon 10/9/06Mon 10/9/06 0%
37
Infinite Campus
1 day?Mon 10/9/06Mon 10/9/06 0%
38
Other Alternatives
1 day?Mon 10/9/06Mon 10/9/06 0%
39      
40
Confirm July 2006 Plan to Pearson
1 day?Fri 12/1/06Fri 12/1/06 0%
41
Centerpoint Implementation (Ongoing)
1 day?Mon 10/9/06Mon 10/9/06 0%
42
On-Line Community Development
1 day?Mon 10/9/06Mon 10/9/06 0%
43
Establish BLOGS
1 day?Mon 10/9/06Mon 10/9/06 0%
44
Snippets
1 day?Mon 10/9/06Mon 10/9/06 0%
45
Comm Comm
1 day?Mon 10/9/06Mon 10/9/06 0%
46
Community Ciouncil
1 day?Mon 10/9/06Mon 10/9/06 0%
47
WHS Board
1 day?Mon 10/9/06Mon 10/9/06 0%
48
Silent Auction
1 day?Mon 10/9/06Mon 10/9/06 0%
49
Other Committees
1 day?Mon 10/9/06Mon 10/9/06 0%
50
Discussion Forums
1 day?Mon 10/9/06Mon 10/9/06 0%
51
Email Lists
1 day?Mon 10/9/06Mon 10/9/06 0%
52
WIKIs
1 day?Mon 10/9/06Mon 10/9/06 0%
53
WHS Gallery /Store
1 day?Mon 10/9/06Mon 10/9/06 0%
54      
55      
56
WHS Technology Plan
1 day?Mon 10/9/06Mon 10/9/06 0%

Resources


IDNameGroupMax UnitsPeak Units
1EAK 100%0%

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
15Enlist Communications CommitteeEAK48 hrsThu 9/28/06Thu 10/5/06100%